San
Antonio Area Freeway System
PROJECT INFO: US
281/Loop 1604 Interchange |
|
| This page
last updated May 8, 2013 |
Work began
in late February 2011 on the first half of a long-planned and equally
long-awaited US 281/Loop 1604 directional interchange. This
project will construct the four southern elevated connectors: US 281
northbound to both directions of Loop 1604 and both directions of Loop
1604 to US 281 southbound. The remaining ramps will not be built
until the future of US 281 north of Loop 1604 is finalized.
In addition to
the four connectors, this project will also make several ancillary
improvements to both US 281 and Loop 1604 in the vicinity.
This project is
being developed and managed by the Alamo Regional Mobility Authority
(ARMA). Funding for the project is coming mostly from the federal
economic "stimulus" program.
Approximately
250,000 vehicles per day pass through the interchange on US 281 and
Loop 1604 with about 20% of them making connections between the two.
This will be the
first five-level interchange in San Antonio.
On this page:
Details
The map below
shows the overall scope of the project. As you can see, it
extends well beyond the actual 281/1604 crossing. Detailed
schematics are available on ARMA's website
here.

Overview of 281/1604 interchange project limits
This will be a
five-level interchange:
- Level 1
(bottom): US 281 mainlanes
- Level 2:
US 281 and Loop 1604 frontage roads
- Level 3:
Loop 1604 mainlanes
- Level 4:
Connectors from US 281 to Loop 1604
- Level 5:
Connectors from Loop 1604 to US 281
In addition to
the interchange ramps, a number of other ancillary improvements are
also proposed for both US 281 and Loop 1604:
- Northbound
US 281:
The existing exit ramp to
Loop 1604/Henderson Pass will be removed to make room for the new exit
to Loop 1604. Motorists wanting to access Henderson Pass and the
US 281 frontage road in that area will use the existing Donella Dr.
exit instead.
In a change from the
preliminary schematics, the exit for Loop 1604 will now be a left-exit
from northbound 281. This was done to preserve the existing exit
ramp at Henderson Pass, eliminate the need to relocate utilities along
the frontage road as well as having to relocate/widen the frontage road
itself, and eliminate the need to reconstruct the existing retaining
wall. Overall, this will shave $5 million off the project and
modestly shorten the construction timeline.
- An
auxiliary lane will be added between the existing entrance ramp from
Bitters Rd. and the existing exit ramp to Thousand Oaks Dr. by
restriping the existing pavement.
- An
auxiliary lane will be added between the existing entrance ramp from
Brookhollow Dr. and the existing exit ramp to Donella Dr. by restriping
the existing pavement.
- Southbound
US 281:
- The
existing entrance ramp from Loop 1604 (just north of Henderson Pass)
will be removed to make room for the new connector entrance from Loop
1604. Motorists on the US 281 frontage road wanting to enter US
281 will continue south and use the existing entrance ramp south of
Donella Dr.
- An
auxiliary lane will be added between the existing entrance ramp from
Thousand Oaks Dr. and the existing exit ramp to Bitters Rd. by
restriping the existing pavement.
- Eastbound
Loop 1604:
- The
existing exit ramp to US 281 will be moved back to just beyond the
Stone Oak Pkwy. overpass to make room for the new exit to US 281.
- An
auxiliary lane will be added from the entrance from Blanco to the exit
for US 281.
- An
auxiliary lane will be added between the entrance from Gold Canyon to
the new exit for Redland (see next bullet.)
- A new exit
for Redland Rd. is planned just east of Mud Creek.
- Westbound
Loop 1604:
- The
existing exit ramp to Gold Canyon Rd. will be removed to reduce
mainlane weaving on the approach to the US 281 exit. Motorists
wanting to access Gold Canyon or the 1604 frontage road would use the
existing Redland Rd. exit instead.
- An
auxiliary lane will be added from the entrance to Redland to the new
exit for US 281.
- The
existing entrance and exit ramps between Stone Oak Pkwy. and Blanco Rd.
will be reversed to better facilitate a new auxiliary lane for traffic
entering from US 281.
- An
auxiliary lane will be added between the existing Blanco Rd. entrance
ramp and the existing Bitters exit ramp.
- Auxiliary
lanes would also be added to the frontage roads in several locations.
- Turnarounds
will be added at the following overpasses on Loop 1604: Bitters Rd.,
Huebner Rd., Gold Canyon Rd., and Redland Rd.
- Continuous
nighttime illumination will be added to Loop 1604 throughout the
project area as well as on the new connectors.
- Sidewalks will
be added to the frontage roads through much of the project area.
- Two pedestrian
overpasses will be constructed over US 281 at Loop 1604 (one on each
side running parallel to the Loop 1604 frontage roads.
-
The Henderson Pass overpass, which has been closed
since the mid '90s, will be mostly torn-down. A small section for
utilities will remain. (This element was
eliminated for technical and cost-savings reasons.)
Renderings
An animated
rendering of the completed project from ARMA is available
here.
Status
Construction is
projected to be completed in Summer 2013. The first connectors
opened
November 8, 2012. In a bit of a surprise, the remaining
connectors opened December 21. The entire project will be
wrapped-up by May
2013.

Estimated ramp completion
dates
|
| |
281 NB
to 1604 WB: |
Open! |
|
|
1604 EB
to 281 SB: |
Open! |
| |
281 NB
to 1604 EB: |
Open! |
|
|
1604 WB to 281 SB: |
Open! |
| |
|
|
|
|
|
|
Project
history
In the late '80s,
US 281 from Bitters Rd. to today's Sonterra Blvd. was upgraded from a
four-lane divided highway to the current six- and eight-lane
expressway. That project added the existing three-level
interchange at Loop 1604. Limited funding at that time precluded
a larger interchange and the three-level configuration was determined
to be adequate for the existing and projected short-term traffic
volumes.
By the mid to
late '90s, TxDOT planners were beginning to evaluate various
improvements to the interchange, including a variation of a
Single-Point Urban Interchange (SPUI) which would have built two
X-shaped bridges through the middle of the existing interchange to
expedite left turn movements, thus allowing for longer green times in
all directions. Because of funding and technical constraints,
that project was never built.
Handouts
distributed at a public meeting in 2000 for proposed improvements to US
281 at and north of Loop 1604 included an artist's rendering of a
proposed five-level interchange at Loop 1604. At that time, it
was listed as a long-term project (beyond FY 2004). Those plans
appear to have formed the basis for the current plans.
Circa 2005, with
funding becoming even more limited, the interchange project was
transferred to ARMA and rolled into the mega Loop 1604 tollway
project. The connectors were proposed to connect to the tolled
"managed" lanes in the center median of Loop 1604 and use of the
connectors themselves would be tolled. Renderings of both the Loop 1604 and
US 281 tollway projects showed the
interchange in this configuration.
In February 2009,
Congress approved a national economic "stimulus" plan that would pour
additional federal money into road construction projects. The
Metropolitan Planning Organization (MPO) approved allocating San
Antonio's share of transportation stimulus funding to be used as
matching funds to leverage state funding for the first half of a
281/1604 interchange. This project would build all four of the
ramps connecting to 281 south of 1604, i.e. northbound 281 to both
directions of 1604, and both directions of 1604 to southbound
281. It was determined that ramps connecting to 281 north of 1604
could not be built until lingering issues stemming from the lawsuits
and associated environmental studies for 281 north of 1604 are resolved
as those ramps would extend into the study area and could prejudice the
possible options. Although the entire interchange had been
previously proposed as a toll-project, the use of the stimulus
funds will allow the ramps to be toll-free. The Texas
Transportation Commission (TTC) approved the funding request on March
5th, 2009.
On March 13th,
2009, it was reported that opponents to the 281 North toll project were
considering a legal challenge to the 281/1604 interchange on the
grounds that it should be subject to a new environmental review as part
of the entire Loop 1604 and US 281 studies. Environmentalists
again hinted in late April 2010 that they might sue to stop the
interchange unless sufficient measures were taken to protect endangered
species in the vicinity. Despite reported negotiations, a lawsuit
was subsequently filed in August 2010. In early February 2011,
the federal judge in the case indicated that he would not be issuing an
injunction against the project prior to hearing the case, which is
currently expected in mid to late 2011. Work on the project
subsequently began in late February. In April 2011, the federal
judge formally denied an injunction against the project. However,
the lawsuit remains pending, although it now almost certainly will be
dismissed as moot.
A 2012 City of
San Antonio bond issue funded approximately half of the cost for the
northern set of connectors with the rest of the funding coming from San
Antonio's recent allocation of Texas Mobility Funds.
Construction on those connectors cannot begin until after the US
281 North environmental impact statement is complete, currently
anticipated in 2014.
Other
sites of interest
|