Home | About me | Contact | What's new
 

San Antonio
Freeway system
  Freeways
    I-10 East
    I-10 West
    I-35 North
    I-35 South
    I-37
    Kelly Pkwy
    Loop 410 (I-410)
    Loop 1604
    SH 151
    Spur 371
    US 90 West
    US 281 North
    Wurzbach Pkwy
  Construction projects
    I-10/DeZavala
    I-10/Leon Springs
    I-35/Loop 410
    I-35/Selma
    SH 151/Loop 1604
    Loop 1604/Braun
    281/1604 intchg
    Wurzbach Pkwy
  Primer
  History
  2011 traffic statistics
  Etcetera
    Media galleries
    Tollway system
      Loop 1604 tollway
      US 281 tollway
    TransGuide
    10/1604 yield signs
    History of 281/410
Other roads & more
FAQ


Twitter

Facebook

Blog

San Antonio Area Freeway System
PROJECT INFO: US 281/Loop 1604 Interchange

This page last updated May 8, 2013

North-Central highlight mapWork began in late February 2011 on the first half of a long-planned and equally long-awaited US 281/Loop 1604 directional interchange.  This project will construct the four southern elevated connectors: US 281 northbound to both directions of Loop 1604 and both directions of Loop 1604 to US 281 southbound.  The remaining ramps will not be built until the future of US 281 north of Loop 1604 is finalized.

In addition to the four connectors, this project will also make several ancillary improvements to both US 281 and Loop 1604 in the vicinity.

This project is being developed and managed by the Alamo Regional Mobility Authority (ARMA).  Funding for the project is coming mostly from the federal economic "stimulus" program.

Approximately 250,000 vehicles per day pass through the interchange on US 281 and Loop 1604 with about 20% of them making connections between the two.

This will be the first five-level interchange in San Antonio.


On this page:


Details

The map below shows the overall scope of the project.  As you can see, it extends well beyond the actual 281/1604 crossing.  Detailed schematics are available on ARMA's website here.

281/1604 Interchange overview

Overview of 281/1604 interchange project limits
 

This will be a five-level interchange:

  • Level 1 (bottom): US 281 mainlanes
  • Level 2: US 281 and Loop 1604 frontage roads
  • Level 3: Loop 1604 mainlanes
  • Level 4: Connectors from US 281 to Loop 1604
  • Level 5: Connectors from Loop 1604 to US 281

In addition to the interchange ramps, a number of other ancillary improvements are also proposed for both US 281 and Loop 1604:

  • Northbound US 281:
    • The existing exit ramp to Loop 1604/Henderson Pass will be removed to make room for the new exit to Loop 1604.  Motorists wanting to access Henderson Pass and the US 281 frontage road in that area will use the existing Donella Dr. exit instead.
      In a change from the preliminary schematics, the exit for Loop 1604 will now be a left-exit from northbound 281.  This was done to preserve the existing exit ramp at Henderson Pass, eliminate the need to relocate utilities along the frontage road as well as having to relocate/widen the frontage road itself, and eliminate the need to reconstruct the existing retaining wall.  Overall, this will shave $5 million off the project and modestly shorten the construction timeline.
    • An auxiliary lane will be added between the existing entrance ramp from Bitters Rd. and the existing exit ramp to Thousand Oaks Dr. by restriping the existing pavement.
    • An auxiliary lane will be added between the existing entrance ramp from Brookhollow Dr. and the existing exit ramp to Donella Dr. by restriping the existing pavement.
  • Southbound US 281:
    • The existing entrance ramp from Loop 1604 (just north of Henderson Pass) will be removed to make room for the new connector entrance from Loop 1604.  Motorists on the US 281 frontage road wanting to enter US 281 will continue south and use the existing entrance ramp south of Donella Dr.
    • An auxiliary lane will be added between the existing entrance ramp from Thousand Oaks Dr. and the existing exit ramp to Bitters Rd. by restriping the existing pavement.
  • Eastbound Loop 1604:
    • The existing exit ramp to US 281 will be moved back to just beyond the Stone Oak Pkwy. overpass to make room for the new exit to US 281.
    • An auxiliary lane will be added from the entrance from Blanco to the exit for US 281.
    • An auxiliary lane will be added between the entrance from Gold Canyon to the new exit for Redland (see next bullet.)
    • A new exit for Redland Rd. is planned just east of Mud Creek.
  • Westbound Loop 1604:
    • The existing exit ramp to Gold Canyon Rd. will be removed to reduce mainlane weaving on the approach to the US 281 exit.  Motorists wanting to access Gold Canyon or the 1604 frontage road would use the existing Redland Rd. exit instead.
    • An auxiliary lane will be added from the entrance to Redland to the new exit for US 281.
    • The existing entrance and exit ramps between Stone Oak Pkwy. and Blanco Rd. will be reversed to better facilitate a new auxiliary lane for traffic entering from US 281.
    • An auxiliary lane will be added between the existing Blanco Rd. entrance ramp and the existing Bitters exit ramp.
       
  • Auxiliary lanes would also be added to the frontage roads in several locations.
  • Turnarounds will be added at the following overpasses on Loop 1604: Bitters Rd., Huebner Rd., Gold Canyon Rd., and Redland Rd.
  • Continuous nighttime illumination will be added to Loop 1604 throughout the project area as well as on the new connectors.
  • Sidewalks will be added to the frontage roads through much of the project area.
  • Two pedestrian overpasses will be constructed over US 281 at Loop 1604 (one on each side running parallel to the Loop 1604 frontage roads.
  • The Henderson Pass overpass, which has been closed since the mid '90s, will be mostly torn-down.  A small section for utilities will remain.  (This element was eliminated for technical and cost-savings reasons.)


Renderings

An animated rendering of the completed project from ARMA is available here.


Status

Construction is projected to be completed in Summer 2013.  The first connectors opened
November 8, 2012.  In a bit of a surprise, the remaining connectors opened December 21.  The entire project will be wrapped-up by May 2013.

Estimated ramp completion dates
 
  281 NB to 1604 WB: Open!     1604 EB to 281 SB: Open!
  281 NB to 1604 EB: Open!     1604 WB to 281 SB: Open!
             

Project history

In the late '80s, US 281 from Bitters Rd. to today's Sonterra Blvd. was upgraded from a four-lane divided highway to the current six- and eight-lane expressway.  That project added the existing three-level interchange at Loop 1604.  Limited funding at that time precluded a larger interchange and the three-level configuration was determined to be adequate for the existing and projected short-term traffic volumes.

By the mid to late '90s, TxDOT planners were beginning to evaluate various improvements to the interchange, including a variation of a Single-Point Urban Interchange (SPUI) which would have built two X-shaped bridges through the middle of the existing interchange to expedite left turn movements, thus allowing for longer green times in all directions.  Because of funding and technical constraints, that project was never built.

Handouts distributed at a public meeting in 2000 for proposed improvements to US 281 at and north of Loop 1604 included an artist's rendering of a proposed five-level interchange at Loop 1604.  At that time, it was listed as a long-term project (beyond FY 2004).  Those plans appear to have formed the basis for the current plans.

Circa 2005, with funding becoming even more limited, the interchange project was transferred to ARMA and rolled into the mega Loop 1604 tollway project.  The connectors were proposed to connect to the tolled "managed" lanes in the center median of Loop 1604 and use of the connectors themselves would be tolled.  Renderings of both the Loop 1604 and US 281 tollway projects showed the interchange in this configuration.

In February 2009, Congress approved a national economic "stimulus" plan that would pour additional federal money into road construction projects.  The Metropolitan Planning Organization (MPO) approved allocating San Antonio's share of transportation stimulus funding to be used as matching funds to leverage state funding for the first half of a 281/1604 interchange.  This project would build all four of the ramps connecting to 281 south of 1604, i.e. northbound 281 to both directions of 1604, and both directions of 1604 to southbound 281.  It was determined that ramps connecting to 281 north of 1604 could not be built until lingering issues stemming from the lawsuits and associated environmental studies for 281 north of 1604 are resolved as those ramps would extend into the study area and could prejudice the possible options.  Although the entire interchange had been previously proposed as a toll-project, the use of the stimulus funds will allow the ramps to be toll-free.  The Texas Transportation Commission (TTC) approved the funding request on March 5th, 2009.

On March 13th, 2009, it was reported that opponents to the 281 North toll project were considering a legal challenge to the 281/1604 interchange on the grounds that it should be subject to a new environmental review as part of the entire Loop 1604 and US 281 studies.  Environmentalists again hinted in late April 2010 that they might sue to stop the interchange unless sufficient measures were taken to protect endangered species in the vicinity.  Despite reported negotiations, a lawsuit was subsequently filed in August 2010.  In early February 2011, the federal judge in the case indicated that he would not be issuing an injunction against the project prior to hearing the case, which is currently expected in mid to late 2011.  Work on the project subsequently began in late February.  In April 2011, the federal judge formally denied an injunction against the project.  However, the lawsuit remains pending, although it now almost certainly will be dismissed as moot.

A 2012 City of San Antonio bond issue funded approximately half of the cost for the northern set of connectors with the rest of the funding coming from San Antonio's recent allocation of Texas Mobility Funds.  Construction on those connectors cannot begin until after the US 281 North environmental impact statement is complete, currently anticipated in 2014.


Other sites of interest

Alamo Regional Mobility Authority - US 281/Loop 1604 Interchange project page
http://www.alamorma.org/US281Loop1604Interchange.html



All donations are much appreciated and are used
to offset the expenses of operating this site.
This page and all its contents are Copyright © 2013 by Brian Purcell

NOTICE
The information provided on this website is provided on an "as-is" basis without warranties of any kind either express or implied.  The author and his agents make no warranties or representations of any kind concerning any information contained in this website.  This website is provided only as general information.  The author expressly disclaims all liability with respect to actions taken or not taken based upon the information contained herein or with respect to any errors or omissions in such information.  All opinions expressed are strictly those of the author.  This site is not affiliated in any way with any official agency.