San Antonio Area Freeway System
PROJECT INFO: US 281/Loop 1604 Interchange |
|
|
This page last updated
September 09, 2011 |
Work
began in late February 2011 on the first half of a
long-planned and equally long-awaited US 281/Loop 1604
directional interchange. This project will construct the
four southern elevated connectors: US 281 northbound to both
directions of Loop 1604 and both directions of Loop 1604 to US
281 southbound. The remaining ramps will not be built
until the future of US 281 north of Loop 1604 is finalized.
In addition
to the four connectors, this project will also make several
ancillary improvements to both US 281 and Loop 1604 in the
vicinity.
This
project is being developed and managed by the Alamo Regional
Mobility Authority (ARMA). Funding for the project is
coming mostly from the federal economic "stimulus" program.
Approximately 250,000 vehicles per day pass through the
interchange on US 281 and Loop 1604 with about 20% of them
making connections between the two.
This will
be the first five-level interchange in San Antonio.
On this page:
Details
The map below shows the overall
scope of the project. As you can see, it extends well beyond the
actual 281/1604 crossing. Detailed
schematics are available on ARMA's website
here.

Overview of 281/1604
interchange project limits
This will be a five-level
interchange:
- Level 1 (bottom):
US 281 mainlanes
- Level 2:
US 281 and Loop 1604 frontage roads
- Level
3: Loop 1604 mainlanes
- Level
4: Connectors from
US 281 to Loop 1604
- Level 5:
Connectors from Loop 1604 to US 281
In addition to the
interchange ramps, a number of other ancillary improvements are also
proposed for both US 281 and Loop 1604:
- Northbound US 281:
The existing exit
ramp to Loop 1604/Henderson Pass will be removed to make room for the
new exit to Loop 1604. Motorists wanting to access Henderson Pass
and the US 281 frontage road in that area will use the existing Donella
Dr. exit instead.
In a
change from the preliminary schematics, the exit for Loop 1604 will now
be a left-exit from northbound 281. This was done to preserve the
existing exit ramp at Henderson Pass, eliminate the need to relocate
utilities along the frontage road as well as having to relocate/widen
the frontage road itself, and eliminate the need to reconstruct the
existing retaining wall. Overall, this will shave $5 million off
the project and modestly shorten the construction timeline.
-
An auxiliary lane
will be added between the existing entrance ramp from Bitters Rd. and
the existing exit ramp to Thousand Oaks Dr. by restriping the existing
pavement.
-
An auxiliary lane
will be added between the existing entrance ramp from Brookhollow Dr.
and the existing exit ramp to Donella Dr. by restriping the existing
pavement.
- Southbound US 281:
- The existing
entrance ramp from Loop 1604 (just north of Henderson Pass) will be
removed to make room for the new connector entrance from Loop 1604.
Motorists on the US 281 frontage road wanting to enter US 281 will
continue south and use the existing entrance ramp south of Donella Dr.
- An auxiliary lane
will be added between the existing entrance ramp from Thousand Oaks Dr.
and the existing exit ramp to Bitters Rd. by restriping the existing
pavement.
- Eastbound Loop
1604:
- The existing exit
ramp to US 281 will be moved back to just beyond the Stone Oak Pkwy.
overpass to make room for the new exit to US 281.
- An auxiliary lane
will be added from the entrance from Blanco to the exit for US 281.
- An auxiliary lane
will be added between the entrance from Gold Canyon to the new exit for
Redland (see next bullet.)
- A new exit for
Redland Rd. is planned just east of Mud Creek.
- Westbound Loop
1604:
- The existing exit
ramp to Gold Canyon Rd. will be removed to reduce mainlane weaving on
the approach to the US 281 exit. Motorists wanting to access Gold
Canyon or the 1604 frontage road would use the existing Redland Rd. exit
instead.
- An auxiliary lane
will be added from the entrance to Redland to the new exit for US 281.
- The existing
entrance and exit ramps between Stone Oak Pkwy. and Blanco Rd. will be
reversed to better facilitate a new auxiliary lane for traffic
entering from US 281.
- An auxiliary lane
will be added between the existing Blanco Rd. entrance ramp and the
existing Bitters exit ramp.
- Auxiliary lanes would
also be added to the frontage roads in several locations.
- Turnarounds will be
added at the following overpasses on Loop 1604: Bitters Rd., Huebner Rd.,
Gold Canyon Rd., and Redland Rd.
- Continuous nighttime
illumination will be added to Loop 1604 throughout the project area as well
as on the new connectors.
- Sidewalks will be
added to the frontage roads through much of the project area.
- Two pedestrian
overpasses will be constructed over US 281 at Loop 1604 (one on each side
running parallel to the Loop 1604 frontage roads.
-
The Henderson Pass
overpass, which has been closed since the mid '90s, will be mostly
torn-down. A small section for utilities will remain.
(This element was eliminated for technical and cost-savings reasons.)
Renderings
An animated rendering of
the completed project from ARMA is available
here.
Status
Construction is
projected to be complete in Summer 2013.

Estimated ramp completion dates
|
| |
281
northbound to
1604 westbound: |
TBD |
|
|
1604 eastbound to
281 southbound: |
TBD |
| |
281
northbound to 1604 eastbound: |
TBD |
|
|
1604
westbound to
281 southbound: |
TBD |
| |
|
|
|
|
|
|
Project history
In the late '80s,
US 281 from Bitters Rd. to today's Sonterra Blvd. was upgraded from a
four-lane divided highway to the current six- and eight-lane expressway. That
project added the existing three-level interchange at Loop 1604.
Limited funding at that time precluded a larger interchange and the
three-level configuration was determined to be adequate for the existing
and projected short-term traffic volumes.
By the mid to late '90s,
TxDOT planners were beginning to evaluate various improvements to the
interchange, including a variation of a Single-Point Urban Interchange (SPUI)
which would have built two X-shaped bridges through the middle of the existing
interchange to expedite left turn movements, thus allowing for longer green
times in all directions. Because of funding and technical constraints, that project was
never built.
Handouts distributed at a public meeting in
2000 for proposed improvements to US 281 at and north of Loop 1604
included an artist's rendering of a proposed five-level interchange at Loop
1604. At that time, it was listed as a long-term project (beyond FY 2004).
Those plans appear to have formed the basis for the current plans.
Circa 2005, with funding
becoming even more limited, the interchange project was transferred to ARMA and
rolled into the mega Loop 1604 tollway project. The connectors were
proposed to connect to the tolled "managed" lanes in the center median of
Loop 1604 and use of the connectors themselves would be tolled. Renderings
of both the Loop 1604 and
US 281 tollway projects showed the
interchange in this configuration.
In February 2009, Congress
approved a national economic "stimulus" plan that would pour additional federal
money into road construction projects. The Metropolitan Planning
Organization (MPO) approved allocating San Antonio's share of transportation
stimulus funding to be used as matching funds to leverage state funding for the
first half of a 281/1604 interchange. This project would build all four of the
ramps connecting to 281 south of 1604, i.e. northbound 281 to both directions of
1604, and both directions of 1604 to southbound 281. It was determined
that ramps connecting to 281 north of 1604 could not be built until lingering
issues stemming from the lawsuits and associated environmental studies for 281
north of 1604 are resolved as those ramps would extend into the study area and
could prejudice
the possible options. Although the entire interchange had been
previously proposed as a toll-project, the use of the stimulus funds will
allow the ramps to be toll-free. The Texas Transportation Commission (TTC)
approved the funding request on March 5th, 2009.
On March 13th, 2009, it was reported
that opponents to the 281 North toll project were considering a legal challenge to the 281/1604 interchange
on the grounds that it should be subject to a new environmental review
as part of the entire Loop 1604 and US 281 studies. Environmentalists
again hinted in late April 2010 that they might sue to stop the interchange
unless sufficient measures were taken to protect endangered species in the
vicinity. Despite reported negotiations, a lawsuit was subsequently filed
in August 2010. In early February 2011, the federal judge in the
case indicated that he would not be issuing an injunction against the
project prior to hearing the case, which is currently expected in mid to
late 2011. Work on the project subsequently began in late
February. In April 2011, the federal judge formally denied an injunction
against the project. However, the lawsuit remains pending and will
likely go to trial sometime in late 2011.
Other sites of interest
|