San Antonio Area Freeway System
History of the Loop
410/US 281 Interchange |
|
|
This page last updated
April 28, 2010 |
On the morning of
June 9th, 2008, the final two ramps in the new $154.7 million,
fully-directional interchange at US 281 and Loop 410 next to San Antonio
International Airport opened, marking the end of an era in San Antonio's
freeway history.
Prior to the interchange's construction,
motorists wanting to go from Loop 410 to US 281 or vice-versa were left
to navigate overburdened surface street and access road connections. This intersection
was often
cited as the only place in Texas where two major urban freeways crossed without
direct connections between them. As a result, traffic frequently queued on Airport Blvd. and the westbound 410 access
road as drivers negotiated their way between the freeways. Only one of the turns
required no interaction with a traffic signal; all of the remaining directions
required motorists to pass through at least one signalized intersection. While
many people simply blamed this traffic nightmare on poor planning, the real story,
as is often the case,
is not that simple. When planning for the North Expressway (US 281) was going on in the late '50s
and early '60s, there were heated debates over the route that the new freeway
should take. After evaluating several routes including San Pedro and Broadway,
a route skirting Brackenridge Park, slipping between the Zoo and Alamo
Stadium, and continuing north over the Olmos Basin was chosen. This route also
caused great protest, but construction on the northern and southern thirds of
the freeway began anyway. Opponents of the route got a federal court order
halting construction on the grounds that the freeway violated a new federal rule
prohibiting freeways from crossing parklands and that the freeway would cause
great disturbance to the animals at the zoo. Meanwhile, the City of San
Antonio, which had been
charged with obtaining the right-of-way for the project, was in the midst of
condemning land for a planned 410/281 interchange. The injunction stopping the
freeway construction caused the City, uncertain as to the future of the project,
to stop dead in its tracks as well. The court battle dragged on for
several years and before long, with development booming along the Loop, owners of the
condemned property demanded that the City either buy the land or release it from
condemnation. Since the freeway seemed doomed at the time, the City lifted the
condemnation and new buildings sprang-up at the interchange site almost
overnight. When the lawsuit was settled and the freeway eventually did come through several years later, the cost of
the land was prohibitively expensive and the interchange was scrapped. (For more
information on the history of 281, see my US 281 North page.)

Proposed
US 281/Loop 410 interchange
This conceptual diagram, from the 1964 San Antonio expressway plan, shows that an
interchange
at Loop 410 and US 281 next to the
airport was indeed planned.
Until the mid '80s, traffic volumes were low enough to allow relatively easy
access between the freeways using access roads and adjacent surface streets.
By the early 1990s, however, traffic volumes began to severely overload this
arrangement. To fix the problem, TxDOT began design work on a four-level interchange. Several preparatory projects in the vicinity were
undertaken in the mid and late '90s including the widening 410
between McCullough and Jones-Maltsberger and the placement of most of the future
ramp pylon pedestals along that stretch. The US 281 overpasses over Loop 410
were also rebuilt and a couple of strategic turnarounds added. Additionally, a
ramp from northbound US 281 directly into the airport terminal area was built. This ramp was proposed and funded separately by the airport and the FAA and was
inserted into the overall interchange construction plan by TxDOT.
After several years of uncertainty over funding, the state finally funded the
entire project in late 2004.
The
project was originally scheduled to be built in five phases over ten years.
However, new funding mechanisms from the legislature allowed the phases to be
combined, saving a considerable amount of time and money. That
consolidated project-- the largest
single highway construction project ever awarded in San Antonio-- was then projected
to take five years to build, but the contractor promised to build it in just over three years. Work continued
almost non-stop, 24 hours a day, seven
days a week and the first ramp to be completed, from 281 southbound to 410
westbound, opened to traffic on the
afternoon of June 18th, 2007. Several additional ramps opened in the
months thereafter and the final two ramps, from both directions of US 281
to eastbound Loop 410, opened less than a year later on the morning of June 9th, 2008, marking the the
end of the storied non-interchange.
|