San Antonio Area
Freeway System
Tollway System |
|
|
This page last updated
September 09, 2011 |
Over the past decade, San Antonio
has boomed, and traffic volumes have increased substantially. At the same time,
funding to build new roads has not been able to keep pace with growth, mostly due to
the effect of inflation and dramatic increases in construction
costs on state's static fuel tax, which has not been
adjusted since 1991, improved fuel mileage, which means less taxes paid
per mile driven, and diversions from the state's Highway Fund to pay for
public education and other non-transportation expenses. Additionally, Texas continues to be
shortchanged by the federal government,
receiving only
about 9 cents back of every dime of the federal fuel tax revenues it
collects, and in 2008 and 2009
the federal government twice rescinded
previously allocated funding due to shortfalls in collections due to
their own static gas tax. San Antonio had fared even
worse, having gotten back only about 75% of its contributions during the
'90s and early 2000s, although
recent changes to funding formulas have improved that ratio
substantially. Still, a substantial backlog of needed projects
remains from all those years of being shortchanged, population and
traffic growth continues unabated across the state adding additional
pressures on an already lagging system, and the funding issues still
have not been resolved by the Legislature.
Therefore, to help
expedite the construction of needed roadways, the state encouraged
regional authorities to find local funding mechanisms. To that
end, Bexar County leaders in 2003 created the Alamo Regional Mobility
Authority (ARMA) to take a local leadership role in finding funding
solutions for the San Antonio area.
Because there are few local funding options available, the primary focus
has been on using tolls as the backing for bonds that would fund major
projects. TxDOT and ARMA estimate that using this financing method
will allow several roads to be built as many as 25 years ahead of
tax-funded estimated schedules and ergo substantially cheaper.
On this page:
Proposed system
ARMA has identified a number of
feasible tollway projects in Bexar County. An initial
"Starter System" of about 20 miles was originally identified
with additional segments
of Loop 1604 subsequently added. Several
other future projects are currently being investigated by TxDOT. The
map below shows the proposed tollway locations in San Antonio as of the
end of 2009.

STARTER SYSTEM
- US 281 North from 1604 to
the Comal County line
- Loop 1604 from
Military Dr. to I-10 East and its interchanges with SH 151, I-10 West, US 281 North, I-35 North, and I-10
East
FUTURE PROPOSED ADDITIONS
- I-35 from Loop 410 South to
the Comal County line
- SH 151 from Loop 1604 to SH
211
- I-10 West from Loop
1604 to Boerne
- I-10 East from Loop
410 to SH 130 in Seguin
- Kelly
Parkway and its interchanges with I-35 South and Loop 410
PREVIOUSLY PROPOSED SECTIONS
(These sections are no longer being considered for tolling.)
- SH 16
(Bandera Rd.) from Loop 410 to Loop 1604
- Wurzbach Parkway from
Starcrest Dr. to Blanco Rd.
- Interchange at Wurzbach
Parkway and US 281
- Southern
half of US 281/Loop 1604 interchange
Types
of tollways
Many people don't understand
how a tollway functions or what it looks like. There are actually several
different types of tollways
being considered for Bexar County:
- Tolled
expressway mainlanes
In
this scenario, the mainlanes of the expressway, which would be new, would be tolled, while
the access roads would remain toll-free. This type of tollway
is currently being considered for US 281 North, SH 151
outside of Loop 1604 to SH 211, and the Kelly
Parkway. Tolled mainlanes for Wurzbach Parkway
between Blanco and Wetmore were studied but determined to be
unfeasible. Bandera Rd. was removed from tollway plans by the
MPO board in October 2009. It is important to understand that
in every case where this type of tollway is being developed, it is
essentially the exact same proposal as a toll-free version of the
project would be. The only difference is that drivers who
opt to use the new expressway lanes would pay a toll. This is
a more "traditional" type of tollway; an example in Texas is the Sam
Houston Tollway (Beltway 8) in Houston.

Animation showing how
toll expressway lanes could be added to an existing divided roadway,
such as on US 281.
- Tolled managed
lanes
On roads that already have toll-free expressway lanes, those existing
lanes would remain
toll-free, but new
express lanes, known as "managed lanes", built
in the median between the existing expressway lanes would be tolled.
The existing lanes would likely have to be shifted outward slightly
to provide sufficient room for the new lanes. The new managed lanes
would be separated from the toll-free lanes by barriers with limited entry and exit
points to the toll-free lanes. It might be possible for the
managed lanes to also double as HOV and/or transit lanes, known as HOT
(High Occupancy/Toll) lanes. This type of tollway is currently
proposed for Loop 1604
and is also being investigated for I-35 and
I-10. This type of facility was recently opened on I-10 West
(Katy Freeway) in Houston.

Animation showing how tolled managed lanes could be added to a typical section of Loop 1604.

Conceptual
rendering of tolled managed
lanes along Loop 1604
(Courtesy: Alamo Regional Mobility Authority)
- Tolled elevated lanes
A tollway would be built elevated over the existing free roadway.
This type of tollway was proposed for Bandera Rd., but studies
showed that it would be unfeasible. This is also one of the
three options currently being studied for US 281 North.
- Tolled interchange
New direct-connect ramps between the tollway and an intersecting roadway
would tolled. Tolled interchanges are currently proposed for
Loop 1604 at SH 151,
I-10 West, US 281 North,
I-35 North and I-10
East, and at Kelly Parkway and I-35 South and Loop 410. A tolled interchange at US 281 and Wurzbach
Parkway was studied but determined to be unfeasible.
The map below shows which type of
tollway is proposed for each tollway segment.

Tolls & toll collection
In late 2007,
the MPO
approved proposed toll rates of 17 cents per mile and 57 cents per tolled
interchange ramp for most passenger vehicles. Larger vehicles
(such as 18-wheelers) would pay 46 cents per mile and $1.15 per ramp.
(These were the planned 2009 rates and are subject to increase based on
inflation rates.) All tolls would be collected electronically; there would be no
tollbooths. Motorists using the tollways would be required to have
an electronic transponder ("toll tag") and a corresponding account with
TxTag, the state's toll tag agency. These tags are mounted in the windshield of the vehicle and
contain an identifier code. Tag readers would be
located at strategic locations along the toll system and would electronically read and record the identifier codes of tags as they
pass by. The toll would then be charged to the account linked to
the tag where it is deducted from a pre-paid balance in the account. Vehicles using the toll system without toll tags
would be photographed and be billed by mail for the toll amount plus an
additional collection fee.
Toll tags from any Texas toll
agency can be used on any tollway in the state.
Schedule, status, and history
Initially, the plan was that TxDOT would build the Starter
System beginning in late 2005, then transfer operational responsibility to ARMA
when completed around 2009. But in May 2005, Cintra-Zachary, the
private consortium selected to build the first leg of the Trans-Texas
Corridor, made an unsolicited bid to build and operate the San Antonio
tollway starter system. After review, TxDOT decided that the
proposal had enough merit that it would seriously consider it, and in
accordance with state law, accepted other private bids to build
and operate the starter system. According to media reports, the
private bid would allow the project to be built faster and would allow
TxDOT to reallocate the $600 million that it would have used to build the
starter system to other projects. After a bit of rancorous debate
between TxDOT and ARMA, it was agreed that the
private plans would be evaluated with local input.
After word of the toll
projects became public, a substantial amount of grassroots opposition,
headed by the Texas Toll Party group that has also vehemently opposed Austin
area toll projects, started to form. They showed en masse at an MPO
meeting in mid 2005 and managed to get the Loop 1604 West extension tabled, at least
for the time being. As you might imagine, these events added
some uncertainty to the entire project. However, TxDOT awarded the
construction contract for the US 281 North tollway (Sonterra to Stone
Oak) in September 2005 and preparation work for construction began in December 2005.
The opponents filed a lawsuit shortly thereafter challenging the project,
arguing that it required a full (and costly) environmental impact
statement (EIS), instead of the numerous environmental assessments (EA) that had
been performed up to that time. Federal law only requires an EIS to be performed
if an EA finds significant impacts, which the EAs for 281 did not.
However, TxDOT and the Federal Highway Administration
(FHWA), who
were both named in the suit, jointly agreed in January 2006 to suspend work on
the 281 tollway project as well as the planned 281/Borgfeld overpass so
that a comprehensive and definitive EA for the
entire corridor could be
done and a subsequent determination made of whether a full impact statement would need to
be performed.
In early 2007, the new EA for
281 was released. As with previous assessments, it found no
substantial issues, a so-called "Finding of No Significant Impacts" (FONSI). The FHWA approved the EA on August 14th 2007. TxDOT
announced plans to cancel the original overpass project at Borgfeld as
ARMA indicated it was considering building the entire 281 tollway project from 1604 to Borgfeld
as one project with construction possibly beginning in 2008.
ARMA is also working on studies on the
other possible toll
projects on I-35 North, Bandera Road, and Wurzbach Parkway. In
early 2007, ARMA determined that the Wurzbach Pkwy. proposal was not
feasible for tolling but is continuing with an environmental assessment
in conjunction with TxDOT for the missing center segment and three proposals for an
interchange at 281. The tolling option for the Bandera Rd. project
was dropped by the MPO board in October 2009.
TxDOT announced in mid-2006 that it was
considering possible toll lanes along I-10 West from Loop
1604 to Boerne and I-10 East from Loop 410 to Seguin. Those would
be additional capacity lanes in the median; the existing lanes would
remain toll-free.
On June 11th, 2007, after a
series of discussions with the Legislature, Governor Perry signed
compromise legislation that put a two-year moratorium on the
construction of privately financed toll roads. The bill included a
number of exceptions, mostly in the Dallas-Fort Worth and Houston areas,
but the 281 and 1604 toll projects in San Antonio were not exempted.
On June 15th, ARMA voted to assume control of those projects with plans
to fund the projects with bonds and begin construction in mid 2008.
In late June 2007, TxDOT
released the results of the EA for the Loop 1604 tollway and expansion
and showed plans for the proposed improvements. That EA also had FONSI
outcome. ARMA has since decided to complete a more comprehensive
EIS for the project.
In December 2007, the MPO
approved the toll rates for the US 281 project. ARMA announced
that they would build the 281 project in two segments: Loop 1604 to
Marshall Rd. and Marshall Rd. to the Comal county line.
Construction on the first segment, from Loop 1604 to Marshall, was
expected to start in mid 2008 with completion in late 2010. The
second segment was expected to be completed in 2012.
In February 2008, toll
opponents and environmentalists once again filed a lawsuit challenging the
latest 281 environmental assessment. After initial arguments, the judge ruled that the
plaintiffs' case had sufficient standing to move forward
with discovery. During the discovery process, TxDOT announced that
they found a document that was omitted from the administrative record for the
federal environmental approval and asked for a 60 day stay to allow time
to submit the document to the FHWA for review to determine if it could
change the overall findings of the study. In early October 2008,
TxDOT then reported that they had uncovered a conflict of interest with
the contractor who performed the endangered species study.
Specifically, it was discovered that a staff biologist with TxDOT was married
to an employee of the company the state had hired to do the a portion of
the study, that the TxDOT employee's supervisor was aware of the
situation and allowed it but that controls put in place to mitigate the
conflict were not enforced. As a result, TxDOT asked the FHWA to
revoke their environmental approval for the project. In November 2008, all
parties involved (TxDOT, ARMA, and the FHWA) agreed to do a more
comprehensive environmental impact statement (EIS) for the corridor and
the lawsuit was dismissed as moot. In April 2009, ARMA hired the consultant to
develop the new EIS and it is expected to be completed by 2012.
Meanwhile, in May 2008, ARMA had selected Cibolo Creek Infrastructure
Joint Venture to design and build the 281 project. The consortium
was
headed by Fluor Enterprises of Irving, Texas, and Balfour Beatty
Infrastructure Inc. of Atlanta, and included several San Antonio
subcontractors. (Contrary to public perception, the consortium
included no foreign companies.) Design work was 30% completed when it was stopped
due to the aforementioned litigation and subsequent decision to do a full EIS. ARMA had planned to start
construction in late 2008 or early 2009 on the first segment, from Loop
1604 to Marshall Rd., with estimated completion in late 2010.
However, those plans are now on hold pending the outcome of the new
environmental impact statement.
In February 2009, a new proposal was made public that would upgrade
281 to a "super-street" from Encino Rio to Marshall. Under the
plan, the intersections of Encino Rio, Evans, Stone Oak, and Marshall
would be redesigned to eliminate straight-through and left-turn
movements on those intersecting roadways. Instead, traffic would
turn right and then use a downstream turnaround on 281 to either turn
back the other way on 281 or get back to the intersecting road and then
turn right to continue through on it. While the plan does add
additional signals and forces some drivers to travel out of
their way, the plan would reduce overall congestion in the area because
it would reduce signal cycles from five or six phases to just two, thus
allowing additional green time for 281 traffic. This proposal is
considered a short-term "band-aid" until the environmental studies for a
more significant upgrade of 281 are complete. For more information
on the super-street proposal, click here.
Also in February 2009, Congress approved a national economic "stimulus"
plan that would pour additional federal money into road construction
projects. The Metropolitan Planning Organization (MPO) approved
allocating San Antonio's share of transportation stimulus funding to be
used as matching funds to leverage state funding for the first half of a
281/1604 interchange. This project would build all four of the
ramps connecting to 281 south of 1604, i.e. northbound 281 to both
directions of 1604, and both directions of 1604 to southbound 281.
The use of the federal funds will allow the ramps to be toll-free.
It was determined that ramps connecting to 281 north of 1604 could not
be built until lingering issues stemming from the lawsuits and
associated environmental studies for 281 north of 1604 are resolved.
The Texas Transportation Commission (TTC) approved the funding request
on March 5th, 2009, and construction began in February 2011.
For more information on the 281/1604 interchange, click
here.
Other sites of interest
|